Indianapolis DPW has provided the Town of Meridian Hills with a tentative schedule for the upcoming Penn Street Bridge project. Please note that the City is working on options to try to expedite the utility locations so that the project can be started and substantially complete in 2024.
Below is Indianapolis DPW’s anticipated schedule for the Penn Street Bridge project:
January 18, 2024: Letting Date
Mid-January 2024 – End of March 2024: Tree clearing may start as early as Mid-January and needs to be completed by the end of March.
January 15, 2024 to October 15, 2024: Utility Relocation Work
April 4, 2025: Latest Date for Bridge Contractor to start work.
*Maximum Road Closure Time – 210 days*
October 15, 2025: Intermediate Completion Date (Roadway Open Date)
June 9, 2026: Final Completion Date
The Town’s Website will be updated as schedule changes are received from Indianapolis DPW.
Thank you,
Colleen Field
Meridian Hills Town Councilor