Calumet is providing materials, services and installation of the Phase 1: 75th Street Sidewalk Project. Contractually, Calumet will be working on this project May 30th through July 31st. Crossroad Engineers will be providing bi-weekly summaries of work progress, a look ahead of what Calumet will be doing for the upcoming 2 weeks, and tracking work days and weather days throughout the project. Also, our July 11 Town Meeting will be providing a progress update.
August 19, 2022 Update: Work completed 8/8 – 8/19 Crossroad Engineers:
Completed all walk, ramp, curb and driveway concrete. Installed the solar powered flashing crosswalk beacons. Opened 75th Street to traffic with only temporary restrictions maintained by onsite crews while working. Fine graded all swales and lawn areas in preparation for mulched seeding anticipated to be on Monday, August 22nd. Finished asphalt in front of ramps. Work for the week of August 22nd also includes pavement markings and removing any unnecessary signage.
Thank you,
Colleen Field