Calumet is providing materials, services and installation of the Phase 1: 75th Street Sidewalk Project. Contractually, Calumet will be working on this project May 30th through July 31st. Crossroad Engineers will be providing bi-weekly summaries of work progress, a look ahead of what Calumet will be doing for the upcoming 2 weeks, and tracking work days and weather days throughout the project. Also, our July 11 Town Meeting will be providing a progress update.
July 22 and July 29, 2022 Update:
From CrossRoad Engineers:
July 22: Construction resumed 7/18 – installed 2 storm drain structures as well as 120 ft. of storm pipe. Started the sidewalk prep for the stretch between Illinois St and Meridian St. This included some clearing of Right of Way and grading.
July 29: 100% complete with storm pipe install and will continue with forming for sidewalk concrete next week.
The previous delay of fiber in the manhole has been resolved – manhole has been installed and fiber has been rerouted.
Calumet will be loading some trench boxes and miscellaneous items on 7/30.
Thank you,
Colleen Field
Meridian Hills Town Councilor